DateBy word of mouthIn TaskMIS
12 OctMonWord of mouthRig back on a temporary seal. “Order the kit.”In TaskMISTwo tasks: the repair (Ishaan, due 16 Oct) and the kit (Sam, due 15 Oct)
13 OctTueWord of mouthNobody is sure the kit was ordered.In TaskMISPO raised; both tasks show what they are waiting for
15 OctThuWord of mouthThe supplier slips. Maintenance hears of it later.In TaskMISBoth dates moved, each with its reason
19 OctMonWord of mouthThe rig still runs on the temporary seal. Nobody asks.In TaskMISOn Aarav’s dashboard: waiting on someone for 3+ days
21 OctWedWord of mouthThe temporary seal is still in.In TaskMISSeal kit fitted, rig pressure-testedCompleted
The rig was running again by 11:30 either way. The difference is that the proper repair had an owner, a date, and a reason every time the date moved.