Scenarios
Everyday work problems, played out step by step.
Situations any Indian factory, site or office will recognise, set at two fictional companies, Beta1, a valve manufacturer, and Alpha1, a construction contractor, with the TaskMIS screens that put the work back on track.
Every scenario is a fictional example, not a customer story.
Manufacturing · 11 scenarios
Production, quality and dispatch
Breakdowns, approvals, supplier dates, dispatch promises and safety walks: the follow-ups that decide whether the plant delivers on time.
Purchase & suppliersManufacturingWhen a supplier’s delivery date changes, who tells production?The foundry changed its delivery date twice. Purchase knew; production and sales kept working to the original plan.
Shift handoverManufacturingWhen the night shift finds a problem, who owns it in the morning?The night-shift supervisor told the morning shift that a fixture was drifting. Everyone heard it. Nobody owned it.
MaintenanceManufacturingWhy does preventive maintenance keep moving to next week?The main lathe’s monthly maintenance was due on 19 October. Urgent orders pushed it back three times in eight days.
MaintenanceManufacturingThe breakdown is fixed. Who owns the follow-up?The hydro-test rig was back on a temporary seal by 11:30. The proper repair needed a kit nobody had ordered.
Customer complaintsManufacturingA closed complaint comes back. Can you show what was done?The corrective action was closed a day early. A week later the customer found one more leaking valve.
CalibrationManufacturingCalibration due while the owner is away. Will the audit find a gap?The gauge calibration dates lived in Kiara’s diary. Then she was away for the week one fell due.
ApprovalsManufacturingWhen the line waits for one signature, does anyone know for how long?First-off parts on the new die were ready at 10. The one person who could approve them was at a customer audit.
DispatchManufacturingA dispatch date is promised. Does every department know its part?Aarav promised the customer a Friday dispatch. Four departments had to finish their part, in order, on time.
Drawing changesManufacturingThe drawing changed after work started. Who moved the date?The customer revised the drawing on Tuesday. The night shift drilled flanges to the old one.
Dealer ordersManufacturingWhy do dealers keep calling the factory for order status?Every dealer called Aarav, and Aarav called production. Some days, five times before lunch.
SafetyManufacturingWhy do the same safety findings come back every walk?Every Saturday’s safety walk found the same things as the Saturday before.
Construction · 6 scenarios
Sites, handovers, the ready-mix plant and the quarry
Snag lists, rain delays, monthly bills, hired machines, cube results and a new M-sand unit: the follow-ups that decide whether a building is handed over on time.
HandoverConstructionThe snag list before handover: who closes each point?The client’s walk-through found 59 snags in Block B. A week later, nobody could say how many were left.
Site scheduleConstructionAfter a week of rain, which delays were really ours?Four days of rain moved the dates at the school site. The late steel hid behind the rain, until the client asked.
BillingConstructionWhy does the monthly bill go out on the 12th?The bill for September’s work reached the clients on 12 October. It had waited on a measurement sheet and a signature.
Hired machinesConstructionThe excavator’s work is done. Who sends it back?The crane’s last lift was on a Thursday. The hire company collected it six days later, and billed every day.
CommissioningConstructionThe new M-sand unit is installed. Why hasn’t it made a tonne?The M-sand unit was installed on 12 October. The power and the supplier’s engineer were both “waiting for them”.
Cube testsConstructionThe 28-day cube result: who is waiting for it?The 28-day result came back on time. It sat in the lab technician’s inbox until the consultant asked for it.
Management · 10 scenarios
Reviews, priorities and the people carrying the work
Weekly reviews, month-end MIS, workload, quotations and growing to a second unit: how management sees what is late or at risk without chasing anyone.
Status updatesManufacturingWhy does a manager’s morning disappear into status calls?A customer asked Aarav one question. Answering it took the whole morning on the phone.
Management reviewManufacturingHow do you run a weekly review without chasing updates?Every Monday, the review hour went into collecting status. By the time the numbers were in, there was no time left to decide.
Month-end MISManufacturingMonth-end MIS without the Excel marathonAnika spent the last two days of every month rebuilding the status in Excel for Monday’s review.
WorkloadManufacturingWhy does one person become everyone’s bottleneck?Every department sent its follow-ups to Sam because he knew the vendors. His delays looked random.
Date changesManufacturingThe deadline moved three times. Do you know why?A jig change moved three times in October. At month end, the three reasons told the same story.
RemindersManufacturingWhen the boss travels, do the follow-ups stop too?Aarav was Beta1’s reminder system. Then he spent a week visiting customers.
Getting startedManufacturingMoving follow-ups out of the WhatsApp group: the first 30 daysBeta1’s follow-ups lived in three group chats, a few notebooks and one Excel sheet. This is the first month of moving them out.
QuotationsManufacturingThe quotation keeps slipping. Who has the costing?The quotation waited on costing, costing waited on production, and then the customer added an option.
PrioritiesManufacturingWhen everything is marked urgent, what gets done first?Sixteen of Beta1’s 22 open tasks were marked High. The export order was one of them.
GrowingManufacturingFrom one unit to two: when informal follow-up stops workingBeta1 opened a second machining unit 8 km away. Walking across the shed to follow up stopped working.
Accounts · 2 scenarios
Collections, renewals and the work around the books
Payment follow-ups after the invoice and the renewals that live in one diary: owned, dated and on record.
CollectionsManufacturingWho follows up the payment once the invoice is sent?Collection calls depended on Anika remembering which invoice was due, and who had promised what.
RenewalsManufacturingWho owns the renewals: licences, AMCs and insurance?The fire NOC, the compressor AMC and the plant insurance all lived in one diary, a week before they expired.