The snag list before handover: who closes each point?

At Alpha1, snag lists lived in the site engineer’s notebook and on the subcontractors’ phones. On the last handover, “almost done” lasted two weeks past the date the client had been promised.

TaskMIS task 1017-0024, Block B snags: replace 6 chipped floor tiles: Porur Apartments, Handover, raised by Meera Nair on 17 Oct, deadline changed once; assigned to Leo Thomas, In Progress, High priority, due 24 Oct in 4 days, was 22 Oct, moved once, Dependency on others, 2 days later; waiting for Tile supplier — same batch since 19 Oct; request External, Meera Nair, 17 Oct; High business impact; nobody copied; what done looks like: from the client’s walk-through on 17 Oct, done = every point closed and re-checked with the client’s engineer, tiles must come from the same batch. The record: raised 17 Oct at 15:15; In Progress 19 Oct; same batch needed for the colour, supplier checking stock; now waiting for the tile supplier; date moved 22 Oct → 24 Oct on 20 Oct, Dependency on others: same batch is at the supplier’s Hosur depot, delivery 22 Oct, fixing 23 – 24 Oct. Shown on Tuesday 20 Oct at 4:10 PM
Task 1017-0024 on Tuesday 20 Oct, 4:10 PM · Alpha1 demo workspace, sample data
See the same two weeks in TaskMIS

Illustrative scenario. Alpha1 is a fictional company. Not a customer story.

Meet Alpha1 — a fictional construction contractor in Chennai, with its own ready-mix plant and quarry.

  • Meera NairMeera · Projects
  • Arjun DasArjun · Site engineer
  • Leo ThomasLeo · Purchase
  • Rohan PillaiRohan · MD · Admin

What went wrong

Fifty-nine points in one notebook.

  1. Walk-throughThe client lists 59 points in Block B.
  2. NotebookThe points are copied out by trade, by hand.
  3. SubcontractorsEach trade is told on the phone.
  4. Handover“Almost done” for two weeks.

One notebook. Three costs.

  • The client loses confidenceEvery slipped handover date is a promise the client has to pass on to the flat owners.
  • A finished building stays on the booksSecurity, cleaning and hired scaffolding stay on until the last point is closed.
  • Every review starts from zeroWith no count by trade, someone walks the floors again to find out.

The same two weeks in TaskMIS

Same snags. Every trade has an owner and a date.

  1. 01 ListSat 17 Oct
  2. 02 Wait19 – 20 Oct
  3. 03 ReviewFri 23 Oct
  4. 04 Hand overSat 31 Oct

Sat 17 Oct · ListSat 17 Oct, 1:00 – 3:25 PM · Seven tasks the afternoon of the walk-through

The walk-through becomes one task per trade, the same afternoon.

Rohan Pillai, the MD, raises the handover itself for Meera Nair, who heads projects: the client’s re-inspection on 31 October. Meera turns the client’s 59 points into five tasks by trade, adds the handover file, and gives each one owner and a date between 22 and 29 October: plumbing, electrical, painting and the file to Arjun Das on site, the tiles and the door hardware to Leo Thomas in purchase.

7 tasks · 59 points · due 22 – 31 Oct

Tasks filtered to the Porur Apartments department, Saturday 17 Oct at 3:40 PM: 7 of 16 active tasks, all Porur Apartments, Handover, Not Started. 1017-0026 Block B handover file: keys, manuals and as-built drawings, Arjun Das, Medium, due 29 Oct; 1017-0025 Block B snags: doors, closers and locks, 8 points, Leo Thomas, Medium, due 23 Oct; 1017-0024 Block B snags: replace 6 chipped floor tiles, Leo Thomas, High, due 22 Oct; 1017-0023 Block B snags: painting touch-up, 22 points, Arjun Das, Medium, due 27 Oct; 1017-0022 Block B snags: electrical, 9 points, Arjun Das, High, due 22 Oct; 1017-0021 Block B snags: plumbing, 14 points, Arjun Das, High, due 23 Oct; 1017-0020 Block B: client’s re-inspection and handover on 31 Oct, Meera Nair, High, due 31 Oct
Tasks → Department: Porur Apartments, Saturday 3:40 PM

19 – 20 Oct · WaitMon 19 – Tue 20 Oct · The tiles wait for the same batch

The one point that depends on a supplier says so, with a new date.

The six tiles must come from the same batch to match. Leo marks the task as waiting for the supplier on Monday. On Tuesday the supplier finds the batch at its Hosur depot, for delivery on the 22nd, so Leo moves the date from 22 to 24 October with that reason. Meera hears it the same day, not at the re-inspection.

The record of task 1017-0024, 5 entries: Meera Nair raised this task on 17 Oct at 15:15, assigned to Leo Thomas, target date 22 Oct, High priority, High impact; Status: Not Started → In Progress, Leo Thomas, 19 Oct, 11:00; Leo Thomas on 19 Oct at 11:20: Same batch needed for the colour. Supplier checking stock; Now waiting for: Tile supplier — same batch, 19 Oct, 11:25; Date moved 22 Oct → 24 Oct by Leo Thomas, 20 Oct: Dependency on others — Same batch is at the supplier’s Hosur depot; delivery 22 Oct, fixing 23 – 24 Oct
The tiles task’s record, Tuesday 20 Oct · append-only, no user can edit

Fri 23 Oct · ReviewFri 23 Oct, 5:50 PM · Four left, eight days to go

On Friday evening the count is one screen, for Meera and for the client.

Electrical, plumbing and the door hardware are closed: three tasks, all on or before their dates. What is left, in date order: the tiles tomorrow, painting on the 27th, the handover file on the 29th and the re-inspection on the 31st. Rohan filters the Dashboard to Porur Apartments, and Export this view gives him an Excel file of exactly that for the client’s project manager.

4 open · 0 overdue · 3 completed, all on time

Dashboard filtered to Porur Apartments, Friday 23 Oct at 5:50 PM, with the Export this view button: open tasks 4, 3 people, 1 department; overdue 0; due today 0; at risk 0; due this week 1, today through Sunday 25 Oct, 1 High priority; completed in the last 30 days 3, 100% on or before the date (3 of 3), 2 today; High priority open 2; on hold or waiting 0
Dashboard filtered to Porur Apartments, with Export this view
Tasks in the Deadline view, filtered to Porur Apartments, Friday 23 Oct: Overdue 0; Due today 0; This week 1: 1017-0024 Block B snags: replace 6 chipped floor tiles, Leo Thomas, tomorrow, 24 Oct, High, moved once; Next week 3: 1017-0023 Block B snags: painting touch-up, 22 points, Arjun Das, 27 Oct; 1017-0026 Block B handover file: keys, manuals and as-built drawings, Arjun Das, 29 Oct; 1017-0020 Block B: client’s re-inspection and handover on 31 Oct, Meera Nair, 31 Oct, High
Tasks → Deadline view: what is left, in date order

Sat 31 Oct · Hand overSat 31 Oct, 2:30 PM · Handed over on the date

The re-inspection passes and the handover keeps its date.

The last snag task closes on the 27th and the handover file on the 29th. On Saturday the client re-inspects every point, signs the handover note and takes the 16 key sets. Rohan’s completion mail shows the handover closed on its first date, never moved; the Archive keeps every Block B task.

Completion mail to Rohan Pillai: Meera Nair completed your task, Block B: client’s re-inspection and handover on 31 Oct. Completed on Sat 31 Oct 2026; target date Sat 31 Oct 2026 — on time; date moved never; reminders sent 2; done by Meera Nair; task #1017-0020
Completion mail to Rohan, Saturday 31 Oct

Completion mail to Rohan

Archive searched for Block B, Saturday 31 Oct: 8 completed tasks. 1017-0020 Block B: client’s re-inspection and handover on 31 Oct, Meera Nair, High, completed 31 Oct; 1012-0011 Return the hired scaffolding at Porur Block B (120 sets), Arjun Das, Medium, 31 Oct; 1017-0026 Block B handover file, Arjun Das, Medium, 29 Oct; 1017-0023 painting touch-up, 22 points, Arjun Das, 27 Oct; 1017-0024 replace 6 chipped floor tiles, Leo Thomas, High, 24 Oct; 1017-0021 plumbing, 14 points, Arjun Das, High, 23 Oct; 1017-0025 doors, closers and locks, 8 points, Leo Thomas, Medium, 23 Oct; 1017-0022 electrical, 9 points, Arjun Das, High, 21 Oct
Archive → search “Block B” · history stays forever, nothing is ever deleted

Try it on your next snag list.

Free for up to 6 members. No credit card required.

Join TaskMIS Today

The difference

Same snags. A different handover.

DateIn a notebookIn TaskMIS
17 OctSatNotebookFifty-nine points in a notebook.In TaskMISOne task per trade, each with an owner and a date
20 OctTueNotebookThe tiles are “coming”.In TaskMISWaiting for the same batch; moved to 24 Oct with the reason
23 OctFriNotebook“How many are left?” Someone walks the floors.In TaskMISThree closed, four left, in date order
27 OctTueNotebookPainting waits for tiles nobody chased.In TaskMISLast snag task closed
31 OctSatNotebookHandover moves to next month.In TaskMISRe-inspection passed; keys handed overOn the date

The client found the same 59 points either way. The difference is that every one had an owner and a date on the day it was found.

What could change

Three outcomes for Alpha1

Every point has an owner the day it is found.

One task per trade, each with one owner and a date before the handover.

FeatureOne owner on every task · A target date is required

The count is a screen, not a site walk.

Filter Tasks or the Dashboard to the site and see what is open, in date order.

FeatureSearch and filters · Four ways to see the work · Management dashboard

The client gets facts, not reassurance.

Export this view gives the client an Excel file of exactly what is open.

FeatureExport to Excel

Possible outcomes in a fictional scenario, not measured customer results.

Used in this scenario

  • One owner on every task
  • A target date is required
  • Departments and sub-departments
  • Search and filters
  • Four ways to see the work
  • Waiting for
  • A reason for every date change
  • Management dashboard
  • Export to Excel
  • Completion mail to the raiser
  • Archive
See every feature on the Product page →

For the owner

Four answers before the handover date

  • How many snag tasks are still open, and with whom?

    Answered in: Tasks · Department: the site
  • What has to close before the re-inspection?

    Answered in: Tasks · Deadline view
  • Is any point waiting on a supplier?

    Answered in: Tasks · Waiting on someone
  • What can we send the client tonight?

    Answered in: Dashboard · Export this view

Start this week

Start with the next walk-through

  1. Give each site its own department, with Handover as a sub-department.
  2. The evening of the walk-through, raise one task per trade with the number of points, an owner and a date before the handover.
  3. Every Friday, filter the Dashboard to the site and send the client the export.

Questions

Quick answers

Can the client see the snag list in TaskMIS?

No. Only your team works in TaskMIS. Export this view on the Dashboard gives you an Excel file to send.

Should every snag point be its own task?

It can be. Alpha1 groups the points by trade, so each task has one owner who answers for all of them, and keeps the point-by-point list in its snag sheet.

Can we attach photos of the snags?

No. TaskMIS does not hold attachments or photos. Keep them where you keep them today and note on the task where they are.